What is a risk assessment matrix?
A risk assessment matrix is a table that turns two judgements – how bad an outcome could be and how likely it is – into a single risk rating. One axis is consequence (or severity). The other is likelihood (or probability). Where the two meet, the cell gives the rating: usually low, medium, high or extreme, shown in green, yellow, orange and red.
The matrix does not find hazards and it does not control them. Its job is to help you put risks in order, so the worst ones are dealt with first, and to give a consistent answer when different people assess the same thing.
The 5×5 risk matrix
The most common form in Australian workplaces has five levels on each axis.
Consequence
| Level | Descriptor | Typical meaning for people |
|---|---|---|
| 1 | Insignificant | No injury, or first aid only |
| 2 | Minor | Medical treatment, no lost time |
| 3 | Moderate | Lost-time injury, temporary impairment |
| 4 | Major | Permanent disability, serious chronic disease |
| 5 | Catastrophic | One or more fatalities |
Likelihood
| Level | Descriptor | Typical meaning |
|---|---|---|
| A | Rare | Could happen only in exceptional circumstances |
| B | Unlikely | Could happen, but not expected |
| C | Possible | Might happen at some time |
| D | Likely | Will probably happen in most circumstances |
| E | Almost certain | Expected to happen |
A rating is read as the consequence number with the likelihood letter – 4C, for example – or as a score where the two are multiplied. Many matrices also rate consequence for property, the environment and reputation alongside people, and take the highest.
How the ratings are laid out
Putting the two scales together gives the grid. A typical layout, reading the consequence number with the likelihood letter:
| A Rare | B Unlikely | C Possible | D Likely | E Almost certain | |
|---|---|---|---|---|---|
| 5 Catastrophic | Yellow | Red | Red | Red | Red |
| 4 Major | Yellow | Yellow | Red | Red | Red |
| 3 Moderate | Green | Yellow | Yellow | Red | Red |
| 2 Minor | Green | Green | Yellow | Yellow | Yellow |
| 1 Insignificant | Green | Green | Green | Green | Yellow |
Organisations draw the boundaries slightly differently, and that is a legitimate choice – but make it once, write it down, and apply it everywhere. The cells that deserve the most thought are the top-left ones: a catastrophic outcome that is rare is still a fatality risk, and should never be allowed to sit in green.
What the colours mean
The colour is an instruction, not a description. A typical scheme:
- Red – high or extreme. Not acceptable. Stop the task, or put controls in place before the work continues. Senior management attention.
- Yellow or orange – medium. Reduce the risk so far as is reasonably practicable. Complete the actions within a set time, often three months.
- Green – low. Keep the existing controls working and check them at each review.
Work health and safety law does not recognise a "tolerable" red. The duty is to eliminate risks so far as is reasonably practicable and, where that is not possible, to minimise them. The matrix tells you where to start.